Information regarding the A338.
Off-peak A338 lane closures 24 – 28 September 2018
There is some preparation works on the A338 coming up next week, which means some off-peak lane closures.
All closures will start at 9.30am and finish at 3.30pm, subject to low enough traffic flow for it to be safe to put out the cones.
Monday
Lane 1 southbound closed from the quarry entrance on the A338 (should only be a short closure)
Tuesday
Lane 1 southbound closed from the quarry entrance down to Cooper Dean. This will be a long closure, and it will appear that not a lot is going on. A Road Restraint Risk Assessment Process needs to be completed. Vegetation clearance outside the water works will also be finished.
Wednesday
Lane 1 southbound may be closed if work from Monday and Tuesday needs finishing.
Thursday
Lane 1 northbound closed from Cooper Dean. This is for the sign base for the scheme information board and Southern Gas Network will be on site to mark out their gas main. Vegetation clearance at Blackwater Junction will also be done.
Friday
Lane 1 northbound closed from Cooper Dean for installation of two signage bases – one at Blackwater and one north of Blackwater.